Transformer Sizing Calculator
Size transformers with demand factors, growth planning, and protection per AS 2374 / AS 60076.
Inputs
0.1 to 1.0 (default 0.8)
0.7 to 1.0 (default 0.85)
Supply Phase
Above 40 °C you are asked for a derating factor
>Sizing margin and derating
50 to 100. Sizes the unit to stay at or below this. Blank: size to 100%, check at 80%
0.3 to 1.0, from the manufacturer
Above 1000 m you are asked for a derating factor
0.3 to 1.0, from the manufacturer
0.3 to 1.0, for non-linear load (or specify a K-rated unit)
>Nameplate impedance and losses
1 to 20. Gives the secondary fault level
For regulation when load loss is not known
HV network at the primary. Blank: infinite source
Iron loss. Needs the load loss as well
Copper loss. Also sets the resistance
>Motor starting
Direct on line: about sqrt(3) x V x locked rotor current / 1000. Needs the impedance
Default 10 (indicative design target)
>Installation
Checks the Cl 4.14.2.2 exception for unprotected secondary conductors
Cl 4.16.2 applies above 50 L
Results
Recommended Transformer Size
160
kVA
Checks
- PassTransformer Loading: 70.59 % (max 80)
Design convention, 80% (indicative)
- PassStandard Size Available: 1 (min 1)
Typical rating series (indicative)
- PassPrimary Voltage Valid: 11000 V (min 1000)
Input range check (indicative)
- PassSecondary Voltage Valid: 400 V (min 100)
Input range check (indicative)
Show the working
| Step | Working | Result | Reference |
|---|---|---|---|
| Calculate maximum demand in kVA | 100 kW x 0.8 demand factor / 0.85 power factor = 94.12 kVA | 94.12 kVA | S = P x demand factor / PF (first principles) |
| Apply future growth percentage | 94.12 kVA x (1 + 20 / 100) = 94.12 x 1.20 = 112.94 kVA | 112.94 kVA | Design allowance (user entered) |
| Select next standard transformer size | Table lookup: smallest standard rating >= 112.94 kVA is 160 kVA (ONAN cooling, 40 degC ambient) | 160 kVA | Typical rating series (indicative) |
| Calculate primary side current | 160 kVA x 1000 / (sqrt(3) [1.732] x 11000 V) = 8.40 A | 8.40 A | I = S / (phase factor x V) (first principles) |
| Calculate secondary side current | 160 kVA x 1000 / (sqrt(3) [1.732] x 400 V) = 230.94 A | 230.94 A | I = S / (phase factor x V) (first principles) |
| Turns ratio | 11000 V / 400 V = 27.5. This is the line voltage ratio, equal to the turns ratio for star-star or delta-delta windings; for delta-star the winding turns ratio is 27.5 x 1.732 = 47.631 | 27.5 | n = Vp / Vs (first principles) |
| Calculate transformer loading percentage | 112.94 kVA / 160 kVA x 100 = 70.59 % | 70.59 % | First principles |
Standards referenced
- AS 2374. Power transformers (rating series used here is indicative, not transcribed)
- AS 60076-1. Power transformers, Part 1: General
Where a lookup value is marked indicative, it has not been transcribed from the current edition of the standard. Check results against your own copy before relying on them for design.
Rated currents from a known rating
Already know the transformer? Enter its rating and voltages for the full-load primary and secondary currents and the turns ratio. Three phase: current equals the rating divided by 1.732 times the line voltage. Single phase: the rating divided by the voltage. It opens with a 200 kVA 11 kV to 420 V unit: 274.9 amps on the secondary, 10.5 amps on the primary, a ratio of 26.19. The turns ratio here is between line voltages; on a delta-star unit the winding ratio is 1.732 times that.
Primary current
10.5A
Secondary current
274.93A
Turns ratio
26.19
Show the working
| Step | Working | Result | Reference |
|---|---|---|---|
| Rating | 200 kVA = 200000 VA | 200000 VA | Input |
| Primary current | 200000 / (1.732 x 11000 V) = 10.5 A | 10.5 A | I = S / (sqrt(3) x V) |
| Secondary current | 200000 / (1.732 x 420 V) = 274.93 A | 274.93 A | I = S / (sqrt(3) x V) |
| Turns ratio | 11000 / 420 = 26.19 (line voltages; a delta-star winding ratio is this times 1.732) | 26.19 | n = Vp / Vs |
Where a lookup value is marked indicative, it has not been transcribed from the current edition of the standard. Check results against your own copy before relying on them for design.
Parameters
Every field this calculator exposes, what it means, the range it accepts, and the traps worth knowing before you rely on the answer.
- Total loadkW
- The connected load the transformer has to serve, in kilowatts of real power. Enter kilowatts, not kilovolt amperes: the power factor field does the conversion. The form accepts 1 to 10,000 kW. Primary voltage, secondary voltage, supply phase and cooling type are also required. Not used when a load schedule is entered.
- Demand factorratio, 0.1 to 1.0
- Scales connected load down to the simultaneous peak. Default 0.8. Gotcha: this is one flat factor applied to the whole load. If you have already worked out maximum demand per AS/NZS 3000 Table C1 or Table C2, enter that figure as the total load and set the demand factor to 1.0, otherwise you apply diversity twice and undersize the transformer. Not used with a load schedule, where each row carries its own diversity.
- Load schedulerows of kW or kVA
- Optional. Each row takes a description, a quantity, a rating per item in kW or kVA, a power factor and a diversity factor from 0 to 1 (default 1). A blank row power factor uses the overall power factor. Rows are added as vectors: kW and kvar are summed separately and the demand is the square root of the sum of their squares. Loads at different power factors therefore add to less than their arithmetic kVA total, which is the physically correct answer. The schedule replaces the total load and demand factor, and its resulting power factor is the one used for regulation and efficiency.
- Power factorratio, 0.7 to 1.0
- Displacement power factor of the load seen at the transformer secondary, used to convert kilowatts to kilovolt amperes. Default 0.85. If the site has power factor correction fitted, use the corrected value. With a load schedule it is the default for rows left blank.
- Supply phasesingle phase or three phase
- This does not change the required kilovolt amperes. It sets the divisor for the currents and the fault current: single phase divides by the voltage, three phase divides by the voltage multiplied by the square root of 3, which is 1.732.
- Primary voltagevolts, line to line
- Typical Australian distribution values are 6,600, 11,000, 22,000 and 33,000 volts. Gotcha: a range check flags any primary below 1,000 volts as a fail, so a low voltage to low voltage isolation transformer shows a failed check even though the kilovolt ampere answer is still correct. Above 1,000 volts a.c. the primary is high voltage under AS/NZS 3000 Clause 1.4.128, and the working notes that Clause 7.6 (AS 2067 in Australia) applies.
- Secondary voltagevolts
- Line to line for three phase or line to neutral for single phase. Typical values are 400 or 415 volts three phase and 230 or 240 volts single phase. A range check flags anything below 100 volts. It is also taken as the no-load voltage when the loaded secondary voltage is worked out from the regulation.
- Future growthpercent, 0 to 100
- Added to the maximum demand before a size is picked. Default 20. The grown figure is the design load used for loading, regulation, losses and efficiency. The day one loading is shown separately.
- Cooling typeONAN, ONAF, AN or AF
- ONAN and ONAF are liquid filled; AN and AF are dry type. It does not change the kilovolt amperes: no forced cooling uprating is applied. It decides whether the liquid dielectric fields apply, and it is named in the ambient warning.
- Ambient temperaturedegrees Celsius
- Design ambient at the transformer location, default 40. Above 40 degrees, the usual normal service maximum, a warning asks for an ambient derating factor. The temperature itself does not derate anything: the factor does.
- Design loading limitpercent, 50 to 100
- Optional. The unit is sized so the design load stays at or below this share of its derated capacity, and the loading check uses it as its limit. Left blank, the unit is sized to 100 percent and the check uses the 80 percent design convention, which is why a selection can pass sizing and still fail the check.
- Ambient, altitude and harmonic derating factorsratio, 0.3 to 1.0 each
- Optional, and entered by you from the manufacturer, a thermal study or a harmonic assessment. The calculator does not generate them. They multiply together into one factor k. The nameplate needed is the design load divided by k (and by the loading limit), and the loading is reported against the derated capacity, rating times k. Uprating above 1.0 is not accepted.
- Site altitudemetres, 0 to 5,000
- Optional. Above 1,000 metres, the usual normal service limit, a warning asks for an altitude derating factor. Altitude itself does not derate anything.
- Impedancepercent, 1 to 20
- Optional nameplate short-circuit impedance on the transformer rating. Gives the secondary fault level, S divided by Z, and the prospective fault current. Needed for the motor starting dip.
- X/R ratioratio
- Optional. With the impedance it splits Z into R and X for the regulation. Ignored, and the working says so, when the load loss is entered, because the load loss sets R directly.
- Source fault levelMVA
- Optional fault level of the high voltage network at the primary. It is converted to a per unit impedance on the transformer base and added to the transformer impedance, which lowers the secondary fault level. Blank means an infinite source, the upper bound.
- No-load loss and load losskW
- Optional nameplate losses. Load loss alone sets the resistance, R percent = load loss divided by rating times 100. Both together give the losses at the design load, no-load loss plus load loss times the per unit load squared, the efficiency, and the load at which efficiency peaks. No-load loss alone is rejected.
- Largest motor starting kVAkVA
- Optional. The starting kilovolt amperes of the largest motor started direct on line, roughly 1.732 times voltage times locked rotor current divided by 1,000. Needs the impedance. The dip is starting kVA divided by starting kVA plus the secondary fault level, and is checked against the starting dip limit.
- Starting dip limitpercent, default 10
- The design limit for the motor starting dip. The default of 10 percent is an indicative design target, not a clause value: AS/NZS 3000 Clause 3.6.2 Note 1 excludes motor starting from its voltage drop limit.
- Secondary conductor ratingamperes
- Optional current-carrying capacity of the conductors on the secondary. AS/NZS 3000 Clause 4.14.2.2 treats them as submains or final subcircuits to be protected under Clauses 2.3 and 2.5. Its exception lets them go without that protection only where the winding supplies a single submain or final subcircuit and the conductors carry at least the rated primary current times the voltage ratio. This field checks that second condition.
- Liquid dielectric volume and flashpointlitres, liquid filled units only
- Optional. AS/NZS 3000 Clause 4.16.2: more than 50 litres of a liquid with a flashpoint not exceeding 250 degrees Celsius needs precautions to prevent the spread of fire. Mineral oil falls in that class. Tick the flashpoint box for a liquid above 250 degrees. At 50 litres or less, Note 2 says preventing escape of the liquid is generally enough. Hidden for dry type units.
Assumptions and limits
This is a demand, size selection and first pass performance tool. Being clear about where it stops is more useful than pretending otherwise.
What the tool assumes
- Without a load schedule, the whole load sits behind one demand factor and one power factor. With a schedule, each row has its own diversity and power factor and the rows add as vectors. There is still no separation of continuous from intermittent load.
- The standard size ladder is a generic list of 10, 16, 25, 50, 63, 100, 160, 200, 250, 315, 400, 500, 630, 750, 800, 1,000, 1,250, 1,500, 1,600, 2,000, 2,500 and 3,150 kilovolt amperes. It is indicative rather than transcribed from AS 2374, AS 60076 or any manufacturer catalogue. Your supplier range may differ. When the requirement exceeds 3,150 kVA the standard size check fails and a warning suggests parallel units.
- The rated currents are at the selected rating, not at the site demand; the secondary current at the design load is shown separately. They ignore magnetising current and tap position.
- The loading percentage compares the design load, which already includes the growth allowance, against the derated capacity (rating times the derating factors). The day one loading is the same comparison before growth.
- The 80 percent loading limit used when no design limit is entered is a common design convention, not a numbered clause requirement.
- Derating factors are yours to enter. The calculator applies them; it does not derive them from temperature, altitude or a harmonic spectrum. Results that rely on them are indicative.
- The fault level is S divided by the total per unit impedance, with no voltage factor, no motor contribution and no cable impedance downstream. It is the symmetrical fault at the transformer terminals.
- Regulation uses the standard approximation, x times (R cos phi plus X sin phi) plus x squared times (X cos phi minus R sin phi) squared over 200, with x the per unit load, at a lagging power factor. Where the point of supply is the low voltage terminals of a substation on the premises, this drop is upstream of the point of supply, and AS/NZS 3000 Clause 3.6.2 Exception 3 allows up to 7 percent from there.
- The motor starting dip is the impedance divider starting kVA over starting kVA plus fault level. It ignores the running load, the cable to the motor and the difference between the starting and short circuit power factors, so it is indicative.
What it does not do
- No thermal or cyclic loading study. Hot spot temperature, loss of life and cyclic overload capability under AS 60076.7 are out of scope. Ambient and altitude only prompt for a factor.
- No inrush or protection sizing and no grading. HV fuse or relay selection and LV main switch selection are separate tasks; the Transformer Fault and IDMT Relay calculators help with them.
- No K factor calculation from a harmonic spectrum, no vector group or neutral earthing selection, and no allowance for transformers running in parallel or in an N plus 1 arrangement.
- No energy cost, loss capitalisation or minimum energy performance check on the losses entered.
- Not a purchase specification. Supply authority connection approval, impedance, losses, noise, and enclosure rating all still have to be agreed separately.
Treat the output as a first pass sizing figure. Check it against the current edition of the relevant standard and have the responsible person for the installation review and sign off the final selection. Nothing here is validated or certified.
Worked examples
Five examples: three phase, single phase, a case where the loading check fails, a derated load schedule, and a full nameplate check of fault level, regulation, efficiency and motor starting. Every figure below comes from the same arithmetic the calculator runs, and examples 4 and 5 are locked as regression tests.
Example 1. Three phase commercial supply, 11 kV to 400 V
A commercial site with 100 kW of connected load fed from an 11 kV network at 400 V three phase. Diversity of 0.8, load power factor 0.85, and a 20 percent growth allowance.
Inputs
- Total load: 100 kW
- Demand factor: 0.8
- Power factor: 0.85
- Supply phase: three phase
- Primary voltage: 11,000 V, secondary voltage: 400 V
- Future growth: 20 percent
Working
- Maximum demand = 100 x 0.8 / 0.85 = 94.12 kVA
- Required rating = 94.12 x 1.20 = 112.94 kVA
- Next standard size at or above 112.94 kVA = 160 kVA
- Primary current = 160,000 / (11,000 x 1.732) = 8.40 A
- Secondary current = 160,000 / (400 x 1.732) = 230.94 A
- Loading = 112.94 / 160 x 100 = 70.59 percent
Pass: loading 70.59 percent is at or below the 80 percent design limit, so a 160 kVA unit is selected with room left over.
Example 2. Single phase rural supply, 11 kV to 230 V
A single phase pole mounted transformer serving 30 kW of rural load at 230 V. Same diversity and power factor assumptions, 20 percent growth.
Inputs
- Total load: 30 kW
- Demand factor: 0.8
- Power factor: 0.85
- Supply phase: single phase
- Primary voltage: 11,000 V, secondary voltage: 230 V
- Future growth: 20 percent
Working
- Maximum demand = 30 x 0.8 / 0.85 = 28.24 kVA
- Required rating = 28.24 x 1.20 = 33.88 kVA
- Next standard size at or above 33.88 kVA = 50 kVA
- Primary current = 50,000 / 11,000 = 4.55 A (no 1.732 factor on single phase)
- Secondary current = 50,000 / 230 = 217.39 A
- Loading = 33.88 / 50 x 100 = 67.76 percent
Pass: loading 67.76 percent is within the 80 percent limit. Note the jump from 33.88 kVA required to a 50 kVA unit, because there is no standard size between 25 and 50 kVA.
Example 3. Industrial site where the loading check fails
A factory with 500 kW connected load, little diversity, and corrected power factor. The required rating lands just above a standard size, so the next size up is barely large enough.
Inputs
- Total load: 500 kW
- Demand factor: 0.9
- Power factor: 0.9
- Supply phase: three phase
- Primary voltage: 11,000 V, secondary voltage: 400 V
- Future growth: 20 percent
Working
- Maximum demand = 500 x 0.9 / 0.9 = 500.00 kVA
- Required rating = 500.00 x 1.20 = 600.00 kVA
- Next standard size at or above 600 kVA = 630 kVA
- Primary current = 630,000 / (11,000 x 1.732) = 33.07 A
- Secondary current = 630,000 / (400 x 1.732) = 909.33 A
- Loading = 600 / 630 x 100 = 95.24 percent
Fail: loading 95.24 percent exceeds the 80 percent design limit. The 630 kVA unit covers the demand but leaves almost no margin at the end of the growth horizon, so step up to 750 kVA or revisit the growth allowance.
Example 4. Load schedule with derating and an 80 percent design limit
A commercial building at 11 kV to 400 V three phase, ONAN, entered as a load schedule. The site runs warm and carries a lot of electronic load, so the manufacturer gives an ambient factor of 0.95 and the harmonic assessment gives 0.9. The client wants the unit no more than 80 percent loaded at the end of the 20 percent growth horizon.
Inputs
- Lighting and power: 120 kW, power factor 0.95, diversity 0.7
- HVAC: 2 x 45 kW, power factor 0.85, diversity 0.9
- UPS: 60 kVA, power factor 0.9, diversity 1
- Future growth: 20 percent, design loading limit: 80 percent
- Ambient derating factor 0.95, harmonic derating factor 0.9
Working
- Lighting: P = 120 x 0.7 = 84 kW, Q = 84 x tan(acos 0.95) = 84 x 0.3287 = 27.61 kvar
- HVAC: P = 90 x 0.9 = 81 kW, Q = 81 x tan(acos 0.85) = 81 x 0.6197 = 50.20 kvar
- UPS: P = 60 x 0.9 = 54 kW, Q = 60 x sin(acos 0.9) = 60 x 0.4359 = 26.15 kvar
- Maximum demand = sqrt(219^2 + 103.96^2) = 242.42 kVA at power factor 219 / 242.42 = 0.9034
- Design load = 242.42 x 1.20 = 290.91 kVA
- k = 0.95 x 0.9 = 0.855, nameplate = 290.91 / 0.855 / 0.80 = 425.30 kVA, so 500 kVA
- Derated capacity = 500 x 0.855 = 427.5 kVA, loading = 290.91 / 427.5 x 100 = 68.05 percent
- Day one loading = 242.42 / 427.5 x 100 = 56.71 percent
- Rated currents: 500,000 / (1.732 x 11,000) = 26.24 A and 500,000 / (1.732 x 400) = 721.69 A
Pass: loading 68.05 percent of derated capacity is within the 80 percent design limit. Adding the rows arithmetically would have given 243.7 kVA of demand, close here because the power factors are similar; the gap widens as they spread.
Example 5. 1,000 kVA industrial unit: fault level, regulation, efficiency and motor start
An industrial site with 680 kW of demand at power factor 0.85 (maximum demand already worked out, so demand factor 1.0), 10 percent growth and a 90 percent design limit. The nameplate gives 5 percent impedance, 10.5 kW load loss and 1.4 kW no-load loss. The 11 kV network fault level is 250 MVA. The largest motor draws 1,300 kVA starting direct on line. The single secondary submain is rated 1,600 A and the unit holds 600 litres of mineral oil.
Inputs
- Total load: 680 kW, demand factor 1.0, power factor 0.85
- Primary 11,000 V, secondary 400 V, three phase, ONAN
- Future growth: 10 percent, design loading limit: 90 percent
- Impedance 5 percent, load loss 10.5 kW, no-load loss 1.4 kW
- Source fault level 250 MVA, motor starting 1,300 kVA
- Secondary conductors 1,600 A, liquid 600 L, flashpoint not above 250 degrees
Working
- Demand = 680 / 0.85 = 800 kVA, design load = 800 x 1.10 = 880 kVA
- Nameplate = 880 / 0.90 = 977.78 kVA, so 1,000 kVA at 88 percent loading
- Clause 4.14.2.2: 52.49 A x 11,000 / 400 = 1,443.38 A, and 1,600 A is at least that
- R = 10.5 / 1,000 x 100 = 1.05 percent, X = sqrt(5^2 - 1.05^2) = 4.8885 percent
- Regulation = 0.88 x (1.05 x 0.85 + 4.8885 x 0.5268) + 0.88^2 x (4.8885 x 0.85 - 1.05 x 0.5268)^2 / 200 = 3.10 percent, so 387.6 V at load
- Source on the 1 MVA base = 1 / 250 = 0.4 percent, fault level = 1 / 0.054 = 18.52 MVA
- Fault current = 18.52 x 10^6 / (1.732 x 400) = 26.73 kA
- Losses = 1.4 + 0.88^2 x 10.5 = 9.53 kW, efficiency = 748 / (748 + 9.53) = 98.74 percent
- Peak efficiency at sqrt(1.4 / 10.5) = 36.51 percent load
- Motor dip = 1,300 / (1,300 + 18,519) x 100 = 6.56 percent, within the 10 percent design target
- Oil: 600 L is more than 50 L, so Clause 4.16.2 fire-spread precautions apply
Pass: loading, secondary conductors and motor dip all pass. The fire-spread precautions for the oil (a bund, curbed area or fire-resisting chamber) still have to be designed in, and the 26.73 kA fault level sets the breaking capacity of the main switchboard.
Transformer Sizing Guide for AS 2374 and AS 60076
Transformer sizing is the process of selecting a distribution or power transformer with sufficient capacity to serve the site load today, with enough margin to accommodate future growth over the asset's 25 to 30 year design life. In Australia, distribution transformers must comply with AS 2374 (power transformers) and AS 60076 (IEC harmonised standard), which specify performance, testing, and rating requirements. The sizing process starts with the maximum demand calculation per AS/NZS 3000, applies demand factors and diversity to determine the actual design load in kVA, adds a growth allowance, and selects the next standard transformer size from the manufacturer's range. This calculator handles each of those steps, applies any derating you enter, and from the nameplate impedance and losses works out the secondary fault level, regulation, efficiency and motor starting dip. It does not size the HV or LV protection.
Key concepts
- Maximum demand vs connected load. The connected load is the sum of all equipment nameplate ratings, but not everything runs at the same time. Maximum demand applies demand factors from AS/NZS 3000 Tables C1 and C2 to calculate the actual simultaneous peak, which is typically 50 to 70 percent of connected load for commercial buildings and 30 to 50 percent for residential developments.
- Standard transformer sizes. Australian distribution transformers are manufactured in standard kVA ratings: 100, 200, 315, 500, 750, 1000, 1500, 2000, and 2500 kVA. Smaller single-phase units (10, 16, 25, 50 kVA) serve rural and light commercial applications. Always select the next standard size above the calculated demand. Non-standard sizes require custom manufacturing with longer lead times and higher cost.
- Growth allowance. A growth allowance of 20 to 30 percent is standard practice for a 20 year design horizon. Undersizing means an expensive transformer replacement within a few years. Oversizing beyond 30 percent increases capital cost and no-load losses (iron losses), which run continuously regardless of load.
- Protection coordination. The HV primary is typically protected by fuses (drop-out or full-range HRC) or a circuit breaker with overcurrent relay. The LV secondary uses a main circuit breaker or switch-fuse. Protection devices must be coordinated so that an LV fault is cleared by the LV protection before the HV fuses operate, preserving supply to other transformers on the same feeder.
Common scenarios
- New commercial building supply. A 6-storey office building with a connected load of 800 kW and diversity factor of 0.65 gives a maximum demand of 520 kW. At 0.90 power factor, the apparent power demand is 578 kVA. Adding 25 percent growth brings the target to 722 kVA. The next standard size is 750 kVA, which would be the selected transformer. The supply authority confirms their network can support this rating at the proposed point of connection.
- Residential subdivision pad mount. A 50-lot residential subdivision with a maximum demand of 4 kVA per lot (after diversity per AS/NZS 3000 Table C1) gives a total of 200 kVA. Adding 30 percent growth for future air conditioning and EV charging brings the target to 260 kVA. A 315 kVA pad-mount transformer is selected. The supply authority may require a larger unit depending on their network planning guidelines.
- Industrial site with large motor loads. A manufacturing facility with 600 kW of process motors and 150 kW of ancillary loads. The largest motor is 110 kW with a starting current of 6 times FLC. The transformer must handle both the 750 kW steady state demand and the transient demand during the largest motor start without an excessive voltage dip, against a limit agreed for the motors and other equipment on site. Enter the motor starting kVA and the impedance to check it. A 1000 kVA unit provides adequate margin for both steady-state demand and motor starting.
Common questions
How do I work out the full-load current of a transformer?+
Divide the rating by the voltage. Three phase: I = S / (1.732 x V) with the line voltage, so a 200 kVA transformer at 420 V carries 200,000 / (1.732 x 420) = 274.9 A on the secondary and 200,000 / (1.732 x 11,000) = 10.5 A on an 11 kV primary. Single phase: I = S / V. The rated currents panel on this page does both sides and the turns ratio.
How do I size a transformer for a building?+
Start from the maximum demand calculation per AS/NZS 3000 Tables C1 or C2. Add a growth allowance (typically 20 to 30 percent for a 20-year horizon). Select the next standard transformer size: 100, 200, 315, 500, 750, 1000, 1500, 2000, 2500 kVA. The transformer must also handle the inrush current from the largest motor starting on the secondary.
What is the standard range of transformer sizes in Australia?+
Common distribution transformer sizes in Australia are 100, 200, 315, 500, 750, 1000, 1500, 2000, and 2500 kVA. Smaller pad-mount transformers for residential subdivisions are typically 315 or 500 kVA. Industrial sites use 1000 to 2500 kVA. Sizes above 2500 kVA use sub-transmission voltages.
What is a demand factor and how does it affect transformer sizing?+
A demand factor is the ratio of maximum simultaneous load to total connected load. It accounts for the fact that not all equipment operates at full power at the same time. Applying demand factors per AS/NZS 3000 typically reduces the required transformer size by 30 to 50 percent compared to the total connected load.
How does growth planning affect transformer selection?+
Transformers are expensive to replace, so most designs include a growth allowance of 20 to 30 percent above the current maximum demand. A site with 400 kVA current demand and 25 percent growth allowance needs a 500 kVA transformer. Oversizing beyond 30 percent increases capital cost and no-load losses.
What protection does a distribution transformer need?+
Distribution transformers typically have HV fuse protection on the primary and LV circuit breaker or fuse protection on the secondary. The secondary protection must coordinate with downstream devices and must clear faults within the transformer short-time thermal limit. The Transformer Fault Calculator determines the secondary fault current for protection coordination.
Saved you time today? Shout the next coffee.
ElecCalc is free, with no login and no paywall, built by a working sparky in Adelaide. A few dollars covers the hosting and keeps the calculators checked against the standards.
On site? Get the same calcs on your phone.
SparkyToolkit gives you offline calculators, AI standards lookup, and on-site drawing tools, all built by the same team behind ElecCalc.
Building something else? DataQuoll serves Australian emergency incidents, river gauges and trade RDO calendars as an API.
Related calculators